Course 02 · Fire Protection Learning Hub

PASSIVE FIRE PROTECTION · STEEL STRUCTURES

Fire-Resistant Coatings for Steel Structures

A practical learning pathway covering system selection and approval, substrate preparation, primer compatibility, adhesion, mechanical reinforcement and field control of thickness and density.

!
Course basis

The course is based on Iran Code 112, first revision dated 2025-10-12. It does not replace specialized Code 830, the product assessment report, technical certificate, project specification or approval authority requirements.

Learning progress0%

Mark each module complete after studying it.

01

Fundamentals

Why does structural steel need fire protection?

Steel is noncombustible, but increasing temperature reduces its stiffness and load-bearing capacity. Fire protection slows the heating rate so the member can maintain structural stability for the required fire-resistance period.

R

Load-bearing capacity

The ability to maintain mechanical and structural function during fire.

E

Integrity

Prevention of flame and hot-gas passage through a separating element.

I

Insulation

Limiting temperature rise on the unexposed surface during testing.

Important distinction

Reaction to fire describes how a material contributes to ignition and flame spread; fire resistance describes how long a member or assembly maintains its required function during fire.

02

System selection

Common passive protection systems for steel

SFRM

Sprayed mineral coating

A thick, lightweight cementitious or gypsum-based layer that limits heat transfer. Adhesion, density and thickness control are critical.

INTUMESCENT

Intumescent coating

It expands under heat and forms an insulating char. It must not be directly covered by other materials and requires space to expand.

ENCLOSURE

Boards or protective enclosure

The member is enclosed by approved boards or a membrane assembly. Continuity, fixings, joints and details govern performance.

Selection principle

Coating type or thickness must not be selected from generic experience; it must come from the product technical assessment and design tables for the actual section, required fire-resistance period and service conditions.

03

Design and documentation

From required fire rating to an approved product

01Required rating
→
02Section geometry
→
03Approved system
→
04Design thickness
→
05ITP and inspection
01

Certificate and assessment report

Factory-produced steel fire protection must have a valid technical assessment appropriate to its type; Code 112 refers to EN 13381 and the legal technical-certification authority.

02

Complete member protection

Columns, primary beams and related members require continuous protection; column protection continues from structural floor to the structural soffit above and includes its connections.

03

No services embedded in protection

Pipes, wiring, ducts or building services must not be embedded within the protection required for an independently protected structural member.

04

Multidiscipline coordination

Suspended ceilings, MEP supports, structural connections, impact guards, anticorrosion paint and future maintenance must be coordinated before application.

ATechnical certificate and scope
BThickness schedule and member map
CMethod statement and surface preparation
DITP, test results and repair records
04

Substrate

Surface preparation and primer compatibility

Steel
Anticorrosion primer
Approved bonding agent if required
Fire protection coating
✓

The surface is free of oil, grease, dust, contamination, loose rust and unsound paint.

✓

The anticorrosion system is explicitly compatible with the fire protection assessment.

✓

An intermediate primer or bonding agent is used only where technically approved.

✓

A mock-up and adhesion test are completed on the actual project substrate before full application.

Chemical incompatibility

Wet cementitious coatings create an alkaline environment. Alkali-sensitive anticorrosion paints, including some alkyd systems, can be damaged; mechanical mesh does not eliminate the need to verify chemical compatibility.

05

Adhesion and reinforcement

Minimum adhesion and when mechanical mesh is needed

Building heightMinimum mineral-coating adhesion
Non-high-rise2.7 kPa
High-rise up to 128 m21 kPa
Above 128 m48 kPa
01

Pre-application testing

Test adhesion to the actual project anticorrosion coating using a project mock-up.

→
02

Acceptable result?

If criteria and dimensional limits are met, application without mesh may be permitted.

→
03

Primer or mesh

Where adhesion is inadequate, use an approved bonding agent or mechanical retention system.

160 g/m²

Minimum mass of continuous galvanized retention mesh where required.

≈ 6 mm

Recommended stand-off distance of continuous mesh from the substrate.

≤ 30 cm

Recommended maximum pin spacing in both directions.

1.5 m

Minimum impact-protection height above finished floor in exposed areas.

Very tall buildings

For buildings above 128 m, the code requires continuous galvanized retention mesh for sprayed mineral protection of steel beams and columns.

06

Quality control

Field inspection: adhesion, density and thickness

ASTM E736 / EN 1015-12

Adhesion testing

ASTM E736 commonly indicates internal cohesive strength, while EN 1015-12 with perimeter cutting can identify failure at the coating-substrate interface.

ASTM E605

Dry-density control

Samples are dried for at least 24 hours at 43±6°C; measured dry density should remain within ±15% of the design dry density.

ASTM E605

Thickness control

For each floor or approximately each 1000 m², at least one column, one primary beam and one secondary beam are checked, using two sections about 30 cm apart.

Thickness acceptance

The average thickness on each member must not be below design thickness. Local deficiency must also remain within the code limits of 6 mm and 25% of design thickness.

If a member fails, the deficient area is repaired and another randomly selected member of the same type is retested.

Quality-control records

01Location map of sampled members
02Thickness, density and adhesion forms
03Equipment calibration certificates
04NCR, repair and retest records
07

Wrap-up

Application checklist and final quiz

Five-question quiz

0 / 5

1. What is the main purpose of fire protection on steel?

2. What is the minimum mineral-coating adhesion for a high-rise up to 128 m?

3. Can an intumescent coating be directly covered by another material?

4. Which properties are checked using ASTM E605?

5. What is required when a member fails the thickness check?

Source and scope

This course summarizes and rewrites the fire-protection-coating provisions in Chapters 8 and 11 of Iran Code 112, first revision. Actual design and application require the complete code, specialized Code 830, the product assessment report and project documents.